Location
Hollywood Road between Baltimore Avenue and Rhode Island Avenue
ABOUT THE PROJECT
The project involves conducting a feasibility study and preparing design plans for a sidewalk on Hollywood Road between Rhode Island Avenue and Baltimore Avenue. There is currently no sidewalk on this street. Design plans will address the steep slope of this street, existing trees and utilities, limited right-of-way and access to the Hollywood Playground and adjoining properties.
STATUS
Request for Proposal for final design (100%) was issued on December 18, 2020. Proposals were due on January 22, 2021. City Council approved an award of contract to Mead and Hunt in May 2021. Design plans 90% complete and under review by the state. Construction bids will be solicited after state approval.
FUNDING
Anticipated Total Design Cost: $100,957.74. Construction funds have not been budgeted. Funding comes from the Federal/State Safe Routes to School grant program in the amount of $79,200 and the balance will be funded by the College Park Complete and Green Streets Capital Improvement Program.
Estimated Completion Date
Design completed - Spring 2022